Customer Retention
655 kWp Across 3 Plants (2022-24)

Grid tied solar systems
655 kWp Across 3 Plants
Commissioned: 2022-24
- In 2022, Gram Oorja conducted an energy demand assessment and commissioned a grid-tied solar solution, adhering to high standards.
- As the predicted generation and actual generation aligned, ensuring the payback was on track.
- Excellent feedback from the first plant led to an order for a more complex second plant, which was completed in 2023.
- Following plant 2’s strong performance, the client commissioned a third plant, completed in August 2024.
Customization . Optimum Generation . AMC & Service

Plant 1: 169 kWp
Commissioned on: Feb 2022
- Solar modules - 445Wp Half-cut mono PERC
- Inverter - 50 kW and 100 kW
- MMS - Aluminum rails on industrial shed
- Annual Generation - 2.32 Lakh kWp
- Annual Savings -22.3 Lakh Rupees
- Solar Modules - 545Wp Half-cut mono PERC
- Inverter - three 50 kW & one 20kW
- MMS - Aluminum rails on industrial shed, supersturcture
- Optimum Utilization Of Space Through Solar Simulation

Plant 2: 195 kWp
Commissioned on: Jul 2023

Plant 3: 291 kWp
Commissioned on: Aug 2024
- Solar Modules - 550Wp Half-cut mono PERC
- Inverter - two 125 kWp
- MMS - Aluminum rails on industrial shed, carport, superstructure
- Protections - ESE certified lightning arrestor, Surge protection, MCCB, String fuses